At John F. Kennedy International Airport, the infrastructure that matters most doesn’t always take up a lot of space. Central Substation 2 (CS2), the first project completed under the airport’s $19 billion “A New JFK” redevelopment program, contains only 18,000 square feet, yet powers two new terminals and a new ground transportation center. It also has capacity reserved for future expansion. Syska Hennessy served as the electrical engineer on the design-build team, with associate partner Ed Fayfman as project manager.
Replacing aging infrastructure
CS2 introduces a modern 15 kV distribution network that will supplement and eventually replace the airport’s 50-year-old 5 kV system. The substation is fed from the Con Edison grid today. It is designed to connect in the future to the on-site cogeneration plant operated by Kennedy International Airport Cogeneration (KIAC), which adds a path to greater efficiency and energy resilience.
Designing out environmental risk
The JFK team specified cast-coil transformers in place of conventional oil-filled units. Removing insulating oil from the equipment eliminated the need for oil-water separation systems and lowered the risk of spills near a site with high groundwater. It also improved fire safety.
Doing more with less
CS2 delivers 40 megavolt-amperes (MVA) from the six-bay, 18,000-square-foot, two-story building. The site was tightly constrained: It is bordered by AirTrain tracks on one side and New Terminal One construction on three others, limited by groundwater, and required to preserve views from the new terminal. A streamlined equipment layout reduced the number of ductbanks and shortened feeder runs. That meant less copper, conduit and concrete, and less of the carbon embodied in them.
Built to belong
Most airport substations are hidden. CS2 was designed to be seen. Its massing, facade and finishes were coordinated with the terminal architects so the building fits into JFK’s new frontage.
A green roof covers approximately 2,500 square feet and water-conscious landscaping supported the project’s LEED Silver certification.
“CS2 demonstrates that advanced technologies and environmental conservation are not mutually exclusive,” Fayfman says. “Responsible engineers can develop designs that prioritize both.”
Delivering responsibly
Lead times for medium-voltage switchgear, transformers and cable doubled during the project. The team responded by specifying modular equipment early, building schedule contingency into the design, and sequencing work around equipment availability. Consequently, CS2 was completed in 30 months.
Eleven companies worked on the project while the airport stayed fully operational.
Staggered, phased installation of 60,000 linear feet of feeders kept construction from disrupting travelers or overall airport operations.
“Complex infrastructure is ultimately built not only with steel, copper and concrete,” Fayfman says, “but with collaboration, trust and shared purpose.”
Awards and Recognition
The American Council of Engineering Companies of New York (ACEC New York) honored CS2 in 2026 with a Diamond Award in the Special Projects category and a Platinum Award in the Energy category. It was also recognized by ACEC National in 2026.
The project partners presented CS2 at the 2026 CMAA Conference. The session, “Accelerated Delivery in a Congested Airport Environment,” highlighted the collaboration behind this complex infrastructure achievement. CS2 was also selected as panel session “Best-value Substation Design Through Change and Collaboration” at the 2026 Design-Build Conference & Expo.
CS2 demonstrates that advanced technologies and environmental conservation are not mutually exclusive. Responsible engineers can develop designs that prioritize both.